South East Water sets out filtration, review and tanker plans for Tunbridge Wells
South East Water has installed new microfiltration at Pembury and commissioned an independent review of risks there, as it sets out how it will strengthen Tunbridge Wells supplies after last year's disruption.
By The Water Wire · Edited by David Bain

South East Water has set out a package of measures to make water supplies to Tunbridge Wells more resilient. It has installed new filtration, commissioned an independent review of risks at Pembury Water Treatment Works and expanded its emergency response arrangements, Greatest Hits Radio Kent reported. The company said some of the improvements are already in place but others will take years to complete.
What we know
According to Greatest Hits Radio Kent, South East Water said:
- Filtration: new microfiltration equipment has been installed at Pembury Water Treatment Works and on a key supply pipe serving Tunbridge Wells. Three temporary activated carbon filtration units are operating at Tonbridge Water Treatment Works.
- Independent review: an independent expert has been commissioned to review potential risks at Pembury. The company said work to address the recommendations is already under way.
- Extra supply: upgrades at Tonbridge are being designed to deliver an additional 2 million litres a day by 2030. Proposals for Bewl could add 7 million litres a day by 2032. Further improvements are planned at Pembury and Bewl.
- Resilience: flood protection and backup power improvements are planned. The company is also investigating a second supply route to a local drinking water storage tank.
- Emergency response: the company has 12 emergency water tankers, a fully staffed 24-hour control room and a newly introduced rapid-response communications team. Its emergency plans cover more than 100 important local sites, including care homes, GP surgeries and special educational needs schools.
- Customer support: it has a dedicated critical care team and a livestock register.
Chief executive John Halsall was quoted as saying "Last year we didn't deliver that". He said some improvements are in place while others "will take longer".
What others are reporting
Water Magazine also reported the microfiltration at Pembury and on the key supply pipe, and the independent expert review. It presented the measures as a response to last year's disruption, with some improvements delivered and more investment planned.
Background
South East Water described its £1.9bn five-year investment programme as the largest in its history, Greatest Hits Radio Kent reported. The coverage did not set out the cost of the Tunbridge Wells measures within that programme. Nor did it give details of the scope of the independent review or name the reviewer.
What to watch
- Whether South East Water publishes the independent expert's findings on risks at Pembury, and its progress against the recommendations.
- Delivery of the extra 2 million litres a day at Tonbridge by 2030, and whether the Bewl proposals progress towards the 2032 target.
- Whether the temporary carbon filtration units at Tonbridge are replaced by permanent treatment.
- Results of the investigation into a second supply route to the local storage tank, and the timing of the flood protection and backup power work.
- Any response from regulators or consumer bodies to the plan.
Sources
- 1Greatest Hits Radio Kent — Tunbridge Wells water supply improvements hellorayo.co.uk ↗
- 2Water Magazine — South East Water outlines measures to strengthen Tunbridge Wells supplies watermagazine.co.uk ↗
Summarised in our own words. Spotted an error? Tell us — we correct visibly.
Read next
More investment →
InvestmentWelsh Water invests £294m in first half and targets more than £600m for 2026/27
Dŵr Cymru Welsh Water says it invested £294m in the six months to 30 September and remains on track for over £600m this year, while admitting it is falling short on leakage, serious pollution and customer experience.
InvestmentSevern Trent invests £1.053bn in first half and plans £25bn supply-chain framework
Severn Trent put £1.053bn into its network in the six months to September, about 37% more than a year earlier, and plans a £25bn supply-chain framework to support future infrastructure delivery.
InvestmentNI Water tenders £29.95m contract for ICA equipment supply and maintenance
NI Water is seeking suppliers across 12 brand-specific lots to supply and maintain its instrumentation, control and automation equipment. The framework could run to 2035 and is meant to improve standardisation while keeping legacy kit supported.
The Current · Free
The UK water industry in two minutes, every weekday.
Sourced, independent, no spin. Unsubscribe any time. Privacy notice.