Ofwat accepts £97,150 undertakings from Albion Water over Northfleet sewage failings
Ofwat has accepted enforceable undertakings worth £97,150 from Albion Water after finding wastewater breaches at Northfleet Eastern Quarry works in Kent. The case is a test of how the regulator polices small independent sewerage operators.
By The Water Wire · Edited by David Bain

Ofwat has accepted enforceable undertakings of £97,150 from Albion Water. The regulator found breaches on wastewater treatment, sewerage provision and the management of regulated activities at Northfleet Eastern Quarry wastewater treatment works in Kent, Water Magazine reported.
What we know
- The breaches. Ofwat found Albion contravened Regulations 4 and 5 of the Urban Waste Water Treatment Regulations and section 94 of the Water Industry Act 1991, according to Water Magazine. The breaches date from when Albion took over the works in November 2020.
- Wider shortcomings. The finding also covers operational management, technical resources and corporate governance.
- Albion's explanation. Albion told Ofwat that excessive wastewater flows contributed to the performance problems.
- Spending to date. Albion reported spending £1.082m on remedial, maintenance and upgrade work at Northfleet by September 2026.
- Reporting. Albion must report to Ofwat on delivery of the undertakings and its compliance plan within 12 months. After that it reports every six months until Ofwat confirms the undertakings have been met.
Ofwat's earlier proposal notice dealt with the works and its discharge permit.
What others are reporting
Water Magazine covered the proposal in September and added these details:
- Ofwat opened its investigation in January 2026, after the Environment Agency raised compliance concerns.
- Ofwat said Albion acknowledged the works had not consistently achieved effective secondary treatment since early 2024. The main cause was hydraulic and organic overloading.
- Albion attributed the high flows to two causes: extra properties being connected, and a cross-connection between the surface water and foul sewer networks.
- Ofwat was initially minded to impose an enforcement order and a penalty of 5% of relevant turnover, equal to £97,150. Albion instead offered undertakings. These cover asset reviews, stronger operational management, enhanced sampling and record keeping, additional technical support and improved governance.
Utility Week described the case as Ofwat's first sewage-failings enforcement against an independent company, known as a NAV. It reported that the offer included completing a £97,150 rainwater harvesting scheme. It quoted Ofwat's finding of "sustained and severe permit non-compliance".
Background
The works serve the Castle Hill development at Ebbsfleet. It was designed for 1,500 properties, a population equivalent of 4,000, and about 600m³ of wastewater a day, according to Water Magazine.
In 2019 Ofwat consulted on giving Independent Water Networks Limited a variation of appointment for Eastern Quarry. The variation would remove the site from Thames Water's water area and Southern Water's sewerage area.
Albion's 2021-22 annual report says it took over the Castle Hill sewerage assets from Independent Water Networks Limited in October 2020. It also says the sale of Albion from Wessex to SDS Limited completed in March 2022.
What to watch
- Albion's first delivery report to Ofwat, due within 12 months.
- Publication of the detailed terms of the rainwater harvesting scheme.
- Whether flows and treatment performance at Northfleet improve as Castle Hill continues to be built out.
Sources
- 1Water Magazine — Ofwat accepts £97,150 undertakings from Albion Water watermagazine.co.uk ↗
- 2Ofwat — Notice of proposal to accept s19 undertakings from Albion Water ofwat.gov.uk ↗
- 3Water Magazine — Ofwat proposes £97,150 redress after Albion Water failings watermagazine.co.uk ↗
- 4Utility Week (subscription) — Albion first NAV to face enforcement over sewage failings utilityweek.co.uk ↗
- 5Albion Water — Annual Performance and Customer Report 2021-22 albionwater.co.uk ↗
- 6Ofwat — Eastern Quarry consultation notice (2019) ofwat.gov.uk ↗
Summarised in our own words. Spotted an error? Tell us — we correct visibly.
Read next
More regulation →
RegulationEssar Oil fined £800,000 for 489 wastewater permit breaches at Stanlow refinery
Essar Oil (UK) must pay £873,473 after admitting Environment Agency charges over trade effluent discharges from Stanlow to watercourses feeding the protected Mersey Estuary between 2018 and 2020.
RegulationSevern Trent confirms compensation after Stourbridge supply loss as MP presses questions
Severn Trent says eligible customers hit by this week's Stourbridge outage will be compensated under the Guaranteed Standards Scheme, as the local MP questions when the outage officially started and what counts as full restoration.
RegulationThames Water submits White Horse Reservoir plans to the Planning Inspectorate
Thames Water has applied for a Development Consent Order for the reservoir near Abingdon, formerly known as SESRO. The Planning Inspectorate now has up to 28 days to decide whether to accept it for examination.
The Current · Free
The UK water industry in two minutes, every weekday.
Sourced, independent, no spin. Unsubscribe any time. Privacy notice.