Skip to content
Friday, 20 November 2026Get the daily brief →

EA modelling: £2.5bn a year could hold flood damages at current levels to 2050

New Environment Agency modelling, reported by Water Magazine, suggests average investment of £2.5bn a year could keep overall flood damages at today's levels to 2050, with surface water taking a growing share of future spending.

By The Water Wire · Edited by David Bain

Abstract illustration: a blueprint of pipe network lines with valves, joined at one amber node.
Illustration: AI-generated for The Water Wire
Original sourceWater Magazine — Environment Agency assessment highlights benefits of doubling flood investmentwatermagazine.co.ukRead ↗

New Environment Agency (EA) modelling suggests that average annual investment of £2.5bn could keep overall flood damages in England at current levels to 2050, according to Water Magazine. The magazine reported the findings on 13 November 2026 under the headline "Environment Agency assessment highlights benefits of doubling flood investment".

The Water Wire has not yet been able to review the EA's own publication, so this report relies on Water Magazine's account as seen in its published summary.

What we know

  • According to Water Magazine, the EA's new modelling indicates that £2.5bn in average annual investment could maintain overall flood damages at current levels through to 2050.
  • The magazine reported that surface water management accounts for a growing share of future investment in the modelling.
  • Water Magazine frames the findings in terms of the benefits of doubling flood investment. The Water Wire has not confirmed the baseline spending figure behind that framing, and it is not reported here.

We have not seen the full set of scenarios, the assumptions behind them, or any statement from the EA or the government. We have also not confirmed the date the EA published the material.

Background

Long-term investment scenarios (LTIS) are the EA's way of modelling how different levels of flood and coastal spending would affect future damages. The approach is not new. A 2016 conference paper by Mike Steel of the EA discusses an earlier edition, and its summary says the EA first published LTIS in December 2014. We have not verified any figures from that paper.

For water companies, surface water is where flood risk most directly overlaps with drainage and sewer networks. That makes the reported rise in its share of future investment relevant beyond the EA's own programme.

What to watch

  • Publication of the full EA scenarios on GOV.UK, including the baseline spend and the assumptions behind the £2.5bn figure.
  • Which surface water measures the EA identifies, and how they relate to water company drainage plans.
  • Any response from Defra or the Treasury on future flood and coastal funding levels.
  • Reaction from water companies, local authorities and industry bodies.

Sources

  1. 1Water Magazine — Environment Agency assessment highlights benefits of doubling flood investment watermagazine.co.uk ↗

Summarised in our own words. Spotted an error? Tell us — we correct visibly.

The Current · Free

The UK water industry in two minutes, every weekday.

Sourced, independent, no spin. Unsubscribe any time. Privacy notice.